會議(yi)地點:科美診斷項目會議(yi)室
時(shi)間:2022年11月26日上午9:30
參加人員:邵兵、王松、謝春華、宋健偉、韓建、黨軍、王立新、盧小芹、劉蘇文、丁十軍、胡啟光、孫治勝、程晉豹、楊樂、陳宣濤、周維建、金永昌、張蘇、陳源、宋雙、吳偉、于洪濤、黃煜、解新民、方衛江、沈偉
會議(yi)內容簡(jian)要:
目(mu)前建筑工(gong)程(cheng)(cheng)項目(mu)陸續推廣盤(pan)(pan)扣(kou)(kou)架支(zhi)(zhi)模(mo)體(ti)系(xi)及(ji)防(fang)護架搭(da)(da)(da)設(she)(she),搭(da)(da)(da)設(she)(she)技(ji)術及(ji)方案(an)還不(bu)夠成熟,在實際運用過程(cheng)(cheng)中需根據項目(mu)特點(dian)(dian)不(bu)斷提(ti)升與總(zong)結。為提(ti)高(gao)公司現場(chang)專監(jian)(jian)、總(zong)監(jian)(jian)的(de)(de)(de)盤(pan)(pan)扣(kou)(kou)架支(zhi)(zhi)模(mo)體(ti)系(xi)的(de)(de)(de)認知(zhi)(zhi),由總(zong)工(gong)辦、工(gong)程(cheng)(cheng)部(bu)在高(gao)新區(qu)科美(mei)診斷項目(mu)組織學(xue)習交流了盤(pan)(pan)扣(kou)(kou)架支(zhi)(zhi)模(mo)體(ti)系(xi)、超長盤(pan)(pan)扣(kou)(kou)頂托施(shi)工(gong)工(gong)藝、盤(pan)(pan)扣(kou)(kou)架高(gao)支(zhi)(zhi)模(mo)搭(da)(da)(da)設(she)(she)等(deng)重點(dian)(dian)工(gong)序施(shi)工(gong)注意要點(dian)(dian),監(jian)(jian)理監(jian)(jian)控(kong)(kong)要點(dian)(dian)等(deng)業(ye)務(wu)知(zhi)(zhi)識。通(tong)過本次學(xue)習交流,監(jian)(jian)理工(gong)程(cheng)(cheng)師(shi)們普(pu)遍有了盤(pan)(pan)扣(kou)(kou)架搭(da)(da)(da)設(she)(she)現場(chang)控(kong)(kong)制(zhi)及(ji)規范(fan)與實際的(de)(de)(de)感(gan)觀(guan)認識,并拿(na)出自己負責的(de)(de)(de)項目(mu)上盤(pan)(pan)扣(kou)(kou)施(shi)工(gong)存在的(de)(de)(de)不(bu)足之(zhi)處拿(na)出來共同探討,優(you)化搭(da)(da)(da)設(she)(she)方案(an)及(ji)驗(yan)收(shou)時注意事項,對參(can)會的(de)(de)(de)監(jian)(jian)理工(gong)程(cheng)(cheng)師(shi)們業(ye)務(wu)知(zhi)(zhi)識的(de)(de)(de)鞏固與提(ti)高(gao)。

1、由馮賽君總監介紹工程概況,組織參會人員進行進入科美診斷項目現場的入場培訓,做到管施工要管安全、管安全要知安全;
2、科美診斷項目專業監理工程師王尊及總監馮賽君,針對該項目盤扣架搭設過程中每個施工步驟、注意事項、先后邏輯順序、監理監控重點、安全風險管控、資料文檔收集重點內容做了一一介紹;
3、方案及日常管控理論知識講解后,項目部總監帶領前來參觀交流的同事們進行現場實物介紹及現場安全管理經驗介紹;
4、共同探討盤扣架超長(chang)頂托(tuo)加雙(shuang)托(tuo)槽鋼(gang)梁的運用技術的受力(li)效果計算與分析(xi);
5、盤扣架超長頂托加雙托槽(cao)鋼梁支模體系拆(chai)模后砼成型觀感參(can)觀。